Can we schedule running of Test Scenarios using the Keyword/hybrid framework you have explained in your tutorial ? If yes than how ?

Can we schedule running of Test Scenarios using the Keyword/hybrid framework you have explained in your tutorial ? If yes than how ? For Example if I need to run test scenarios in excel during night time .

Add Comment
  • 1 Answer(s)

    You can create  time scheduled job using continuous integration tool Jenkins which will execute below command

    java -cp lib/jar*  org.testng.TestNG <path to testng.xml>

    that will run all the methods/classes/suite mentioned in testng.xml